The 1,465 housing units permitted during the first six months of 2005
exceeds the second highest year, 2001, by 275 units, or 23% and last year’s
six month total by 669 units or 84%. The permitted value of these units,
excluding land, exceeds the second highest year, 2001, by $115,389,115, or
63%. This year’s total building value falls only $11.1 million short of the
total for the last two years combined.
The major contributors to these enormous increases are the following six
communities: Bella Terra,
Villagio,
Osprey Cove,
Rapallo,
Meadows and
Belle Lago.
The average building value of $203 thousand almost equals 2004 in spite
of the fact that the percentage of single family homes is 24% lower.
REMINDER: The residential building value understates the cost of each
residence because it excludes the value of the underlying land.
Estero's 2005 property tax base grew by a record $860 million. This
increase is almost $240 million larger than our previous high growth period
in 2002. This year’s increase is larger than Estero’s total property tax
base just six years ago. With this year’s housing starts being far ahead of
all prior years and Estero’s commercial growth just getting underway we
would predict that Estero’s 2006 property tax growth will easily exceed $1
billion.
The Lee County Tax Appraiser's preliminary 2005 data shows Estero’s
property tax base to be $4.2 billion. That value is about 10 times what it
was nine years ago in 1996 and nearly four times as large as 5 years ago, in
2000.
As a result of this growth Estero’s tax base is now:
• about 4 percent greater than the City of Fort Myers,
• 37 percent greater than the City of Fort Myers Beach, and
• less than 1 percent smaller than the City of Sanibel.
On July 13th several representatives of Simon Property Group and two of
their developers met with members of the EDRC to present their design plans
for Estero’s largest retail and mixed use development, the
Coconut Point Town Center. The Town Center is a 166 acre parcel on the northeast corner of
Coconut Road and US 41. When complete It will consist of three shopping
areas – The Market, the Lakefront Shops and The Village.
View an Exciting Video of Simon’s Plans for the Coconut Point Town Center
on the web at
www.coconutpointretail.com
Simon began the presentation with a five minute video prepared for the
International Shopping Center Convention. The following details have been
changed since the video was prepared:
• There will be a fountain in the arrival court,
• A dome on the east side of the Village was changed to a tower with a
tile roof,
• Some other changes due to changing tenants and their needs.
Simon stressed that the redesign effort emphasized creating a sense of
variety by using many Mediterranean features. Applicant used many towers as
strong corner elements.
A disk with the drawings of most all of the buildings was provided to
EDRC member Joe McHarris who agreed to make copies for the rest of the
committee to review.
There will be a mixed use area along the east side of the Village with
residential over retail. On the other side of the main street there will
also be office over retail. The first floor retail in these buildings is
higher than usual giving these two story buildings the appearance of being
three stories tall. The view of Main Street is always changing because that
road is designed as an arc rather than a straight street.
Simon will be maintaining the buildings and property as these as leased
spaces.
Pedestrian level decorations (banding, cornices etc.) are made of precast
stucco and stone while those higher up are foam extrusion. The site plan
keeps the rear of most of the buildings from public view.
Kosene and Kosene, the developer, and Wakefield Beasley, their architect,
discussed the residential portion of the project. Kosene is another
Indianapolis, Indiana firm that specializes in urban residential
development. They will be developing seven buildings…three along the Main
Street and four free standing residential buildings, containing a total of
289 units. Parking for all of the units will be under some of the strictly
residential buildings. The project will include 16 floor plans varying in
size from 1,000 to 2,400 square feet under air. Units are expected to sell
for $250,000 to $500,000.
Some other characteristics of The Residences at Coconut Point are:
• Each unit will have a private balcony,
• All the buildings will use the same color schemes and barrel tile
roofs as elsewhere in the town center,
• There will be a clubhouse, pool, spa and exercise area,
• Grillwork, attractive fencing and landscaping will hide the garage
areas,
• The maximum height of the buildings is 45 feet making it difficult to
add towers; however parapets might be possible.
• The design will hide the mechanical equipment on the roof,
• All windows will be hurricane impact resistant,
• Three bridges will connect the residential/retail buildings to the
residential buildings with the under-building parking,
• A question arose as to what people from the
Brooks could see. The
developer stated that site line studies were done and the nearest
residents of The Brooks would not be able to see these buildings,
• The heating and air conditioning system will not require any thru the
wall grills and their condensers will be on the roof.
The Simon Property Group continues to work with the Lee County Sheriff to
locate a substation in the Village. The Market section of the project is due
to open in March 2006 with the balance of the project planned to open in the
fall of 2006.
Simon will return to the EDRC to present its signage, landscape and
lighting plans when the designs are complete. Simon assured the EDRC that
all the designs would satisfy the Coconut Point Design Guidelines approved
by the community and County staff. The landscaping plans will include
street, building and building perimeter planting plans.
Due to increased construction costs the Muvico Theater has been downsized
so that it will now consist of 16, rather than 20, screens and 3,500 seats.
About two thirds of the front of the Theater will be screened from view by
other buildings. There is a 10 foot walkway between the front of the theatre
and the buildings that screen it form view. Simon stated this area would be
a secure area and would be used only as a theatre exit. The Simon Property
Group will be providing security for the entire project. The EDRC was not
impressed by the architecture and design of the Muvico Theater noting that
it’s architecture is different than all the other buildings in the project.
In addition the EDRC stated that the rear of the theatre needs to be better
landscaped. The Muvico representative agreed to return with an architectural
plan more in line with the rest of the shopping center and that has been
coordinated with the overall Simon design and approved by the Simon prior to
resubmission. A detailed landscape plan must also be provided.
The following seven roadway projects are scheduled for construction in
and around Estero during the next two and one-half years. They must stay on
schedule if south Lee County is to avoid even more traffic gridlock over the
next several years as Estero’s residential growth rate increases and our
commercial growth takes off.
With the help of FDOT and Lee DOT staff this and subsequent EDR reports
will identify the key schedule deadlines for each project so that any delays
are observed and corrected as soon as possible.
Construction Underway…Completion Date…August 2005
Construction Underway…the completion date for the segment excluding the
bridge over the Imperial River is January, 2006 with the bridge segment
expected to open in April, 2006
|
Action |
Responsible Party |
Planned Date |
Actual Date |
|
Apply for State Infrastructure Bank (SIB)
Construction Loan |
Regional FDOT |
August 2005 |
|
|
Decision on the SIB Loan Application |
State FDOT |
November 2005 |
|
|
60% Design Complete |
Regional FDOT |
|
Complete 6-05 |
|
Community Meeting |
Regional FDOT |
Fall 2005 |
|
|
90% Design Complete |
Regional FDOT |
Early to mid 2006 |
|
|
ROW Complete |
Regional FDOT |
Early 2007 |
|
|
Start Construction |
Regional FDOT |
|
|
Construction in the new adopted work program is funded in fiscal year
2009/2010, although Florida DOT along with Lee County and the ECCL are
exploring options to advance construction to 2006/2007 when the project will
be production ready.
Today, Florida DOT has $146 million programmed in fiscal year 2007/2008
to six-lane I-75 from Golden Gate Parkway in Collier County to Daniels
Parkway in Lee County. $67 million is programmed to six-lane the interstate
from Daniels Parkway to SR 80 in fiscal year 2009/2010.
In recent years, Florida DOT has made interim interchange improvements
along I-75 to help relieve congestion at interchanges during peak travel
times. Minor interchange improvements are now underway at Corkscrew Road. A
new interchange at I-75/Golden Gate Parkway is under construction that will
provide more direct access to Naples. It is expected to be completed in the
summer of 2007. Cost for this new interchange is $26.5 million.
Major interchange reconstruction starts this week at I-75/Alico. This $32
million job rebuilds and improves the efficiency of one of the most heavily
used interchanges in Southwest Florida. The contractor expects to finish the
job by the end of 2006.
The north end of this segment connects to Three Oaks Parkway at East
Terry Street.
Monthly Progress: Many more properties acquired, now over 60% of
all Right of way (ROW) properties have been acquired.
Important Challenges: Coordinate the engineering firm that is
supporting both the County on this project and the City of Bonita Springs on
the East Terry widening project regarding the intersection designs and ROW
acquisition at the Dean Street and East Terry Street intersections. Satisfy
the South Florida Water Management District’s permit requirements regarding
the overpass over the Imperial River.
|
Action |
Responsible Party |
Current Activity |
Completion/ Date |
|
Complete Dean Street Intersection Design |
Lee DOT & City of Bonita Springs |
Coordinating with Bonita Springs |
|
|
Acquisition of E. Terry Street Intersection
Property |
Lee DOT & City of Bonita Springs |
Coordinating with Bonita Springs |
|
|
60% Design Complete |
Lee DOT |
|
Completed |
|
All Permits Approved |
Lee DOT |
Revisions for SFWMD being completed |
|
|
100% Roadway Design |
Lee DOT |
Final review |
Complete 7/05 |
|
Bridge Plans |
Lee DOT |
90% complete |
|
|
Right of way maps |
Lee DOT |
|
Complete 6/05 |
|
Select Contractor |
Lee DOT |
Late 2005/early 2006 |
|
|
Begin Construction |
Lee DOT |
January 2006 |
|
|
Complete Construction |
Lee DOT |
June 2007 |
|
Monthly Progress: Progress has been made regarding the contract
necessary to acquire the Centex property, but the contract has not yet been
finalized. This is the largest and most complicated ROW acquisition needed
for this project.
Important Challenges: Obtain BOCC approval of the mitigation bank
to be used for this project. Staff has recommended the Corkscrew Mitigation
Bank but two other mitigation banks are competing for the business. The BOCC
needs to decide this issue at its August 2nd meeting. Water Management
District and Corps of Engineers permits cannot be obtained until this issue
is resolved. Thus delay in this decision will delay the bidding process and
the project.
|
Action |
Responsible Party |
Current Activity |
Completion/ Date |
|
100% Right of way plans |
Lee DOT |
Field surveys in process |
|
|
Complete Tisone/Centex Acquisition Contract |
Lee DOT |
Under negotiation |
|
|
Complete Other Property Acquisitions |
Lee DOT |
Many approved by the BOCC on 6-29 |
|
|
|
|
|
|
|
Permit Approval |
Lee DOT |
SFWMD’s only issue is the mitigation credit
issue |
|
|
Roadway Design Complete |
Lee DOT |
Final Report Under Review |
Complete |
|
Request for Bids |
Lee DOT |
Draft documents under review |
|
|
Open Bids |
Lee DOT |
|
|
|
Select Contractor |
Lee DOT |
|
|
|
Begin Construction |
Lee DOT |
January 2006 |
|
|
Complete Construction |
Lee DOT |
June 2007 |
|
Monthly Progress: Progress is being made in mitigation
negotiations with the Water District and the Corp of Engineers.
Important Challenges: Acquisition of three major parcels from two
owners that are necessary for detention ponds required by this project and
the Estero Parkway Flyover.
|
Action |
Responsible Party |
Current Activity |
Completion/ Date |
|
Property Acquisition |
Lee DOT |
|
|
|
Permit Approval |
Lee DOT |
SFWMD awaiting environmental supplement for
final approval |
|
|
Roadway Design |
Lee DOT |
Finalizing for 100% submittal |
August 2005 |
|
Request for Bids |
Lee DOT |
|
|
|
Open Bids |
Lee DOT |
|
|
|
Select Contractor |
Lee DOT |
|
|
|
Begin Construction |
Lee DOT |
October 2005 |
|
|
Complete Construction |
Lee DOT |
April 2007 |
|
Monthly Progress: Site preparation and clearing continues on the
Corkscrew to Williams Road segment since June. Storm sewer installation
continuing on the Coconut to Williams Road segment.
|
Action |
Responsible Party |
Planned Date |
Actual Date |
|
Start Construction Phase 1 – Coconut to
Williams Road |
Oakbrook Properties and the Simon Development
Group |
May 2005 |
May 2005 |
|
Start Construction Phase 2 – Corkscrew Road to
Williams Road |
Oakbrook Properties and the Simon Development
Group |
May 2005 |
June 2005 |
|
Start Construction – Coconut Road to Pelican
Colony Boulevard |
Oakbrook Properties and the Simon Development
Group |
July 2005 |
July 2005 |
|
Complete Construction Phase 1 – Coconut Road to
Williams Road |
Oakbrook Properties and the Simon Development
Group |
March 2006 |
|
|
Complete Construction Phase 2– Corkscrew Road
to Williams Road |
Oakbrook Properties and the Simon Development
Group |
August 2006 |
|
|
Complete Construction – Coconut Road to Pelican
Colony Boulevard |
Oakbrook Properties and the Simon Development
Group |
August 2006 |
|
Monthly Progress: Right of way acquisition now 85% complete.
Important Challenges: Mitigation negotiations with the Water
District and the Corps of Engineers must be completed before the project can
be permitted. All available road contactors have more work than they can
handle so competition for new projects is limited. In addition the County
will soon have 5 or 6 projects ready to bid. Not all of them can be bid at
the same time. Thus some will be delayed, and the costs are likely to be
higher, because the supply side of the market is so limited.
|
Action |
Responsible Party |
Current Activity |
Completion/ Date |
|
Air rights agreement |
Lee DOT |
Working on legal description |
|
|
Right of Way Acquisition |
Lee County |
September 2005 |
|
|
Permit Approval |
Lee County |
Coordination re mitigation |
|
|
90% Bridge Plans |
Lee County |
Underway |
|
|
90% Roadway Plans |
Lee County |
Completion expected in November 2005 |
|
|
Approved Construction Financing Available |
Lee County |
October 2005 |
|
|
Begin Construction |
Lee County |
May 2006 |
|
|
Complete Construction |
Lee County |
|
|
Each summer Lee County
Department of Community Development publishes a report assessing the “Level
of Service” for each road segment in the county, among other public assets.
In the report the county uses the most recent traffic counts to grade each
road segment’s ability to handle the current traffic. Roads that are
handling the traffic best are accorded a grade of “A” and those that are
failing will be assigned a grade of “F”.
When the developer of a commercial project seeks a Development Orders
(DO) for a project, the County uses the concurrency information and the
traffic impact statement for the project to decide if the DO can be approved
without causing the adjacent roads to fail. If an adjacent arterial roadway
is predicted to fail when the proposed project opens for business, the
County can deny the DO and the project cannot proceed until the road is
improved.
The recently released report contains information on two Estero road
segments that may delay major retail projects that will soon be seeking
Development Orders or rezoning. They are:
• The segment of Corkscrew Road between Three Oaks Parkway and I-75.
During both 2003 and 2004 this segment received a grade of “D”. Projects
under review on this segment include the
Embassy Suites,
Arizona Pizza,
Hampton Inn, a 40,000 square foot medical office building,
Classic Car Wash,
a 168,000 Lowe’s store, 25,000 square foot of small stores in the
Estero
Town Commons. In addition traffic on the road will be increased by the fall
2006 opening of the Coconut Point Town Center and several other commercial
developments west on Corkscrew Road and south on US 41.
• The segment of Coconut Road between Spring Creek Road and US 41. During
both 2003 and 2004 this segment received a grade of “D” although the volume
of traffic in 2004 was about 20% higher than in 2003. Traffic on this
segment is increasing due to continuing construction in the
Hyatt Time-share
development; the Colony in Pelican Landing and in Coconut Shores. Future
development of the former Weeks Fish Camp property and the JED development
on the 46 acre parcel on the northwest corner of Coconut and US 41 may be
delayed until this segment or the intersection is improved.
With the
construction of Gulf Coast Town Center at Alico and I-75 the developers are
widening Ben Hill Griffin from Alico to one mile south of that intersection.
This project is now underway and is expected to be completed in October. The
County’s 2020 long range transportation plan calls for Ben Hill Griffin to
be six-laned down to Estero Parkway. A substantial part of the impact fees
paid by the Gulf Coast Town Center are set aside for this widening project,
but traffic conditions do not warrant this expansion today.
The first phase of Gulf Coast Town Center is also scheduled to be
completed in October. The stores expected to open at that time are:
• Super Target
• Linens ‘n Things
• Petco
• Babies “R” Us
• Jo-ann Etc.
• Regal Cinema
The second phase, to be opened in the fall of 2006, will include:
• Bas Pro Shops
• Belk, and
• J C Penney.
Earlier this month Lee
Memorial Health Systems closed on the purchase of 22 acres in the section of
Coconut Point that lies south of Coconut Road. The property is located
adjacent to the Bonita Community Health Center.
The purchase agreement prohibits Lee Memorial from building more than
30,000 square feet of medical space and more than 100,000 square feet of
office or retail space prior to 2009. This restriction would not preclude
the development of a free-standing emergency department. Florida law
prohibits the development of such facilities until July 2006. If such a
facility is to be approved for the site Estero and Bonita residents will
need to work with the Lee Memorial to persuade the legislature to provide
the necessary legal authority. This facility would permit major emergencies
to be handled locally rather than requiring transport to the nearest
hospitals about 10 miles away. Alternatively Lee Memorial could use the land
and the existing building authority to expand the existing Community Health
Center.
Thus this site will not be home to a south Lee County hospital for at
least five years. If Lee Memorial wants to proceed with a hospital in 2009
they would need to seek an amendment of the existing Development of Regional
Impact (DRI) zoning. According to press reports Lee Memorial’s studies
suggest that by 2015 a 200 bed full service hospital may be needed in the
area.
Between February 16th and July 1st the Chief Lee County Hearing Examiner
heard six days of testimony regarding
Cingular Wireless PCS’s, formerly
AT&T, rezoning request that would permit a long established cellula