|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
![]() |
The two required public hearings on these changes are scheduled before the Board of County Commissioners on January 14, and January 28, 2003, at 5:05 p.m. Accelerating Construction of Three Oaks ParkwayIn late October County DOT published a report on Three Oaks Parkway, the third major north-south road corridor connecting Naples and Ft. Myers. The DOT Report summarized "the status of all the segments of the Three Oaks/Imperial/Livingston projects from Daniels Parkway to the Collier County line, providing a realistic estimate of the production schedules of each phase)… . As demonstrated in the attachments, however, the advancement of the Three Oaks South construction phase is not really a matter of money – it is limited by production constraints." (Underline added for emphasis). As we reported in October the Report projected a gloomy picture regarding completion dates for the Three Oaks segments important to Estero, most of it due to the long permitting periods included in the forecast. The report's forecast for the four segments in our area:
The County Report suggested one way these dates might be accelerated. Since then meetings with County DOT, County Commissioners and local developers have generated two additional ideas for accelerating these critical road projects. Area Wide Mitigation StrategyFor some time the County has been pursuing an area wide mitigation strategy with the Federal environmental permitting agencies to define an overall mitigation scheme to meet the that would satisfy the needs for all the roads in our the county Capital Improvement Plan and ultimately in their long range plan. Once this has been accomplished each road project would be required to do its share of the overall mitigation scheme. If approved this approach is expected to make the roadway permitting process much shorter. County Financing of U. S. Corp of Engineers Project Permitting ReviewerFederal law, the Water Resource Development Act (WRDA), authorizes local governments to fund U. S. Corp of Engineer (COE) staff positions whose sole responsibility is to review that government's selected public projects requiring COE permits. The program has been used by several Pacific Northwest governments with great success and is supported by Lee County Transportation staff. Unquestionably the Federal government should be providing these services in a timely manner at their expense. Just as surely they have consistently failed to do so and the Federal budget now under consideration by Congress does not contain funding for additional COE reviewer positions. Each Corp permit review position costs the sponsoring local government about $135,000 per year. On the other hand the roadway construction delays caused by the Federal permitting process are annually costing Lee County millions of dollars. Recently COE permits delayed the construction of Alico Road by two or more years. As a result of the delay the cost of this road segment increased by $1 million. During 2002 the cost of the Bonita Springs segment of Three Oaks Parkway between Terry Street and Coconut Road increased by $10 million. Some of this increase was caused by the City's decision to change the alignment of the road, but a substantial part resulted from the increased right-of-way and construction costs brought about by the two year delay caused by the City of Bonita Springs taking over the alignment decision from the County after incorporation. We have been told that one Corp reviewer typically processes six projects per year. With land values in south Lee County escalating rapidly, county funding of one COE position is likely to save the county several million dollars per year at a cost of less than $150,000. In spite of these facts the BOCC has twice failed to support the issues related to this proposal. Commissioners Albion and Judah have been consistently supportive while Commissioners Coy and St Cerny have been consistently opposed on philosophical grounds. Commissioner Janes apparently opposed the proposal the first time it was considered and procedural rules prevented him from supporting it the second time. We are hopeful that he will sponsor the proposal and bring it back to the BOCC in the near future. We urge our readers to communicate their support of the proposal with all the commissioners during the next couple of weeks. County Representation in WashingtonCommissioner Janes is a strong advocate of Lee County having representation in Washington on both policy and Federal funding purposes. According to the National Association of Counties (NACo) more and more county governments are being represented in our nation's capital each year. The Federal government is a major source of funding for many county functions including transportation, housing, health care, education, beach renourishment, immigration and pubic safety to name a few. If the county hopes to satisfy any Federal funding needs in 2003, it must contract with a Washington representative no later than the end of February when proposals have to be submitted to key Congressional appropriators. 2003 offers two important opportunities for Federal support of county funding needs: 1. The nation's transportation funding legislation is extended every five years -- 2003 is one of those years, and 2. The homeland security legislation recently approved by Congress authorizes several billion dollars for local governments to improve their public safety and anti-terrorist programs.Discussions with several experienced Washington representatives of county governments suggests that county staff needs to review and prioritize its Federal government policy and funding needs before selecting and contracting with a Washington representative. Once these priorities have been determined the Estero community would, no doubt, be able to identify how some of its needs could be satisfied by the county's representative. The Lee County Port Authority Board has been represented in Washington by the law firm of Hogan & Hartson for about 8 years. Some advantages or efficiencies may be realized by the county if it were to use the same firm. Estero Roadway Median Landscaping UpdateAt present six Estero roadway landscaping projects have been funded and are in process of being designed or installed. Three of them -- Corkscrew Road, Three Oakes Parkway and the University Overlay -- will be completed in 2003, one in 2004 and the third in early 2005. Upon completion of these projects over 50% of Estero's major roadways will have large canopy trees in their medians. University Overlay Landscaping of Ben Hill Griffinfrom Alico Road to Corkscrew Road and corkscrew Road from Ben Hill Griffin to I-75Recently this project has been bid and the final contract value assigned for each category of work. The project is scheduled for approval by the BOCC at their first meeting in January. Following Board approval the project manager will issue subcontract agreements and begin construction. Thus installation of the irrigation lines is expected to start in about one month (at the end of January). Three Oaks Parkway in The Brooksfrom Coconut Road to the Bonita Springs BorderThe Bonita Bay Group is now constructing this half mile segment of road that will link up to the Bonita Springs segment that has recently been delayed for two years due to anticipated Federal permitting delays. Construction is expected to be completed during the first quarter of 2003 at which time the road will be landscaped in the beautiful Brooks style. US 41 from Old 41 to Corkscrew RoadWilson Miller has been selected by the county to design the "core" level roadway landscaping for this 3.5 mile segment including.7 mile in Bonita Springs. The City of Bonita Springs recently agreed to participate in the landscaping design contract. Consequently the County is now renegotiating the Wilson Miller contract to add the Bonita segment to the design project. Upon completion of this amendment Wilson Miller will commence designing the landscaping for this segment. Simultaneously the Simon Group and Oakbrook Properties are working with Florida DOT to revise the roadway design so that the turn lanes needed for the Coconut Point project can be constructed during the six laning project. This is timely since these changes will impact the landscape design. In addition FDOT has recently adopted new "Clear Zone" rules that will not permit large trees (with trunks over 4 inches in diameter at maturity) to be planted in this road at this time. We anticipate that these trees may be added once Coconut Point is up and operating. Corkscrew Roadfrom Sandy Lane to Corkscrew WoodlandsThe County Roadway Landscape Advisory Committee (RLAC) approved the preliminary detailed plans (60%) for "intensified" landscaping of this road segment at their meeting on December 3rd. "Intensified" landscaping approximately doubles the number of trees planted along the roadway from the number typically installed under the county "core" landscaping program. Also during December the County began to install the trees that had previously been ordered for the "core" landscaping of the road in accordance with the revised plan. The landscape designers must submit their final (90%) plans to the county by January 8th. Once these plans and the related irrigation plans have been approved by the county, the county and the contractor will negotiate an amendment to the existing installation contract. Then the "intensified" landscaping installation can begin. The "intensified" landscaping design for Corkscrew Road not only contains many large trees in the medina but also many trees in the right-of-way along the north side of the road. It is not possible to plant trees in the south right-of-way due to utility lines and easements. This project is moving ahead speedily and will be the first county roadway landscaping project completed with "intensified core" landscaping made possible by the $2 million increase in this year's county budget for landscaping. Three Oaks Parkwayfrom Williams Road to Corkscrew Roadthe first draft of the "intensified" roadway landscape plan for this segment have just been submitted to the county and will be discussed at the RLAC meeting on January 7th. Final design plans are scheduled for completion in March whereupon installation contract bidding can begin. Koreshan Boulevardfrom US 41 to Three Oaks ParkwayOn Tuesday, December 3rd, the County Roadway Landscape Advisory Committee chose this Koreshan Boulevard project and one other project (the two highest rated under their competitive rating system) to fund under the County's $500,000 program for landscaping existing county roadways. This recommendation will be transmitted to the Board of County Commissioners shortly for their approval. Once approved by the BOCC the County can contract for the landscape design work. The design of projects like this usually takes about four months. Then the County can solicit bids for the installation of the plantings and upon selection of the contractor installation can begin, probably in the fall of 2003. This $282,000 investment by the County would not have been possible without the support of the five principal landowners along this stretch of Koreshan Boulevard who agreed to enter into a contract with Lee County to pay the cost of maintaining the landscaping for the first year after installation. The contract between the county and the landowners provides that should the county decide to "intensify" the landscaping that the landowners will pay the increased cost of the first year's maintenance. The county recently indicated its willingness to "intensify" the landscaping along Koreshan. Thus by this time next year the county should be installing about $550,000 worth of trees in the median of this road. They will nicely complement the extensive landscaping now being installed along the south side of the road by Rookery Point and The Cascades. Toll Brothers has indicated it plans to install extensive frontage landscaping by its development when it is constructed on the north side of the road. The property owners and developers that made this possible are:
Estero Community Planning Panel (ECPP)When the ECPP met on December 10th Sean Weeks of SRW Engineering, Randy Wilkerson of Design Builders of Florida and David Jones of David Jones and Associates, presented plans for Estero Palms, a 10-acre site on the south side of Block Lane between River Ranch Road to the east and the site of the new Estero Community Park to the west. The site is just north of Estero High School. Developer Wilkerson proposes a gated community with two cul-de-sacs containing 32 upscale single-family homes situated on lots of approximately 75 x 100 feet. The proposal includes sewage, landscaping, sidewalk and roadway improvements on Block Lane. To be included in the project is a Block Road walkway to the new community park for the estimated 500 current and future residents of Block Lane. In addition to the zoning request the developer is seeking county approval for a development order for phase one of the project. Approval is expected in January at which time infrastructure improvements will be started on the eastern part of the site. If the rezoning is approved by April 2003 the entire infrastructure will be completed by November or December 2003. Dan DeLisi, the ECPP's planner and an Estero resident, has left the firm of Vanasse & Daylor (V&D) and another V & D planner will be assigned to the ECPP account. Also during December the county's sign control staff met to adapt the ECPP proposed Land Development Code sign changes into language that county staff can effectively enforce. These changes are expected to become available to the ECPP in January. Estero's 2002 Permitted Housing Unit GrowthDuring November, only 63 housing units were permitted in Estero, the lowest total since December 2001. Year to date 1,418 housing units have been permitted in Estero, about 30% less than last year's peak rate. Even with the slowdown, thus far this year Estero has produced 26% of the residential building permit value, excluding land, for all of unincorporated Lee County. Estero's share of the building value of all permitted construction year to date is 22%. The value of residential housing units permitted in Estero thus far this year is more than double that of Bonita Springs, $258 million to $124 million. Estero's year to date permitted commercial building value is only 42% as large as Bonita's. Overall the building value for all kinds of properties permitted in Estero during 2002 exceeds Bonita Springs by 45%.
![]() |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||